Projects. Renovation, Jumeirah, Dubai.

Beach Center

Client side BIM management on behalf of ARM Holding for the renovation of a beach centre and a new G+2 car park. Independent clash testing on the contractor's own models, weekly reviews against the BEP, and the BIM requirements the model is delivered and handed over against.

Role
Client side BIM Manager
On behalf of
ARM Holding
Organisation
Bureau Veritas
Platform
Navisworks, ACC

1

The project

Renovation and new G+2 car park

The renovation of an existing beach centre and the construction of a new three storey car park beside it, modelled by the contractor in Revit and federated in Navisworks. My role sits on the client side, on behalf of ARM Holding: making sure what is delivered in the model is what the employer asked for, and that gaps are closed before they become site problems or a weak handover.

Federated model of the beach centre and car park

2

Independent clash testing

Navisworks

Rather than accept the contractor's clash reports, I ran the tests again on their own federated model. On the beach centre, structure against mechanical, the contractor's 5 mm tolerance hid 28 clashes, 8 clashes marked resolved were still clashing, and 147 had an overlap above 25 mm. Every result was located to the nearest grid and level and given a priority, so the contractor receives a list they can act on.

 Contractor testIndependent test
Tolerance5 mm0 mm
Open results305347
Marked resolved568 of them still clashing
PriorityNoneP1 to P3 on every result
Duct running through a concrete beam, found in the independent test

3

Coordination the model has to carry

MEP across disciplines

The services are where a renovation goes wrong: new ductwork, pipework and cable routes threaded through an existing structure. Each weekly review checks the MEP models against structure and architecture, and against the BIM Execution Plan, the clash matrix and the ISO 19650 naming convention for files and families.

Mechanical, electrical and plumbing services inside the beach centre

4

Preparing the BIM requirements for ARM Holding

BEP, ACC issue tracking, clash matrix, naming, LOIN

On behalf of ARM Holding I set out the BIM documents the project needs before coordination can be trusted: a BIM Execution Plan, issue tracking on Autodesk Construction Cloud, a clash matrix, an ISO 19650 naming convention for files and families, and a level of information need matrix. Each is tracked in the weekly report with its due date and status. The LOIN matrix, issued as Appendix B Rev 02, covers 122 element rows across eight disciplines and defines what each element must carry at LOD 300, 400 and 500.

Weekly report page tracking the five requested BIM documentsArchitecture sheet of the LOIN matrix, Appendix B Rev 02

Want the detail behind any of this?

Happy to walk through the clash method, the BIM requirements or how the weekly review is run.